Lower Whitefish Lake Shoreland Restoration RFP

Description: Clearing trees in the project limits and using them to obtain root wads with a trunk section, keying in riprap along the shoreline interbedded with root wads, grading the slope to a side slope of 2.5 horizontal to 1 vertical, placing armormax 75 system turf reinforcing mat on lake side slopes, grading of back slopes in some locations, temporary sedimentation and erosion control, and vegetation restoration. The construction sequence and schedule are left to the contractor's discretion. It is believed that materials like riprap, excess soil and debris from clearing and grubbing can be brought in or out during the winter period.

Buyer
Released
Oct 29, 2026
Closes
Dec 4, 2026(7 days left)