Summary
Class A gravel; clay and silt content not to exceed five (5) percent. It shall be the duty of the contractor to remove immediately any gravel material rejected by the inspector if so ordered. Gradation Requirement, Percent Retained - Minimum, Maximum 1 inch -- 0% 3/4 inch sieve 2% 10% #4 sieve 25% 50% #10 sieve 80% 100% #200 sieve 95% 100% All gravel loaded on county trucks shall be performed on any or all days of the week between hours of 7:00 a.m. and 5:30 p.m. except Saturday and Sunday. The contractor must have on his property a stock pile of a minimum of 2,500 yards of road surfacing gravel at all times that shall conform to the specifications of the State of Nebraska Class A gravel. The bid price will be for CYD's and be good from January 1, 2026 to December 31, 2026.