Summary
The project generally consists of installing approx. 450 LF of 8" gravity sanitary sewer along the southeast quadrant of the property being developed, adjacent to I-70 right-of-way. The project also includes the construction of a new lift station at the southeast corner of the property. The lift station will pump flow via approx. 2,900 LF of new 4" force main under I-70 and adjacent to I-70 and SR49 right-of-way, continuing south before connecting to the City's existing gravity sewer system adjacent to the McDonald's property. The sanitary force main beneath I-70 will be installed via directional bore within a casing pipe. Work also included in the project is a water main extension across SR49, which will also be installed via direction bore with a casing pipe. The approx. 370 LF of new 6" water main will connect to the existing water main system and extend to the property to provide water service to future developments.