Summary
Coordination with Digsafe. Location and mapping of existing utilities in the project area. Contractor must be familiar with high risk, tight digs, and preferably have experience with jetting capabilities. Must use certified flagging company during any work within the roadway Coordination with Vermont Electric Coop to stabilize a utility pole adjacent to project area. Coordination with H2O innovation for water shut off and relieve pressure from system. Removal of abandoned pipe off mainline. Perform all pressure testing and backfill of area to ensure stabilization and future integrity of line. Coordinate line flushing and boil water notice with businesses, operators, and board. Complete cleanup and site preparation for concrete, topsoil, seed and hay. Be sure to advise H2O Innovation when water quality testing is needed.