Summary
Furnish, weld and install approx. 7,665 LF of HDPE solid-wall pipe ranging from 26" to 6" with welded side-saddle turnouts, tees, and delivery assemblies ranging from 2" to 10", associated mobilization, selective demolition, tree removal, trenching, earthwork, backfill, compaction, surface restoration other restoration, coordination for utilities, utility relocations, coordination with owner and owner's engineer and all other associated meter assemblies, stub turnouts, cleanouts, air and vacuum valve assemblies, valves and valve cans necessary to provide a complete project, ready for irrigation delivery.