Septic System Replacement: Abandon the existing system and install
1050-gallon concrete tank and new drainfield, including a grinder
pump and septic sand. rainfield Installation: Install 650 sq. ft. of drainfield, deliver and place septic sand, and remove old drainfield materials. Hydro Tank Rehabilitation: Sandblast and coat a 5000-gallon hydro tank interior/exterior. Set up a temporary bypass system to ensure the facility is not without water during sandblasting and coating. Electrical-permitting and coordination with an electrical
subcontractor with the septic installation and emergency generator.
Utility Area Coordination: Maintain access to water valves, septic
tanks, propane tanks, generators, and other marked zone