Summary
The work generally consists of the expansion of the existing Pump Station site area, including all excavation and embankment for this site work, a new 100,000 gallon welded steel ground storage tank and foundation, related yard piping and valves, connections to existing pump station yard piping, placing flexible base drive area and all final site grading, fencing and restoration. Currently, the existing tank filling operation is not automated. The water level in the existing tank tracks the level in the City of Burnet