CityMA
Posted
Oct 6, 2026
Nov 4, 2026
FY27 Road Drainage Improvements
Work includes approx 556 CY unclassified excvation; 1,350 LF of 12" HDPE plastic pipe; 4,840 LF of hot mix asphalt berm; 60 LF of 4' chain link fence - black.
Description: Work includes 100 EA inlet protection (va e&sc std. 3.07 & vdot std. Ec-6); 2,500 SY erosion control / soil stabilization matting (vdot std. Ec-2 & ec-3); 100 TN riprap culvert outlet, ditch, and slope protection (class ai riprap, vdot std. Pg- 3); 100 TN riprap culvert outlet, ditch, and slope protection.
City · VA, US
From the first pre-RFP signals to the published RFP and its files.
Budget
47 days before RFP
The adopted CIP planned $20,000,000 for East Ocean View drainage improvements, with Phase II design ongoing and finalization expected in summer 2026.
FY 2027-2031 Adopted Capital Improvement Plan Improve East Ocean View Drainage Storm Water Management Enhancing Community Beautification and Maintenance Adopted FY 2027 Planned FY 2030 Planned FY 2029 Planned FY 2028 $0 $5,000,000 $5,000,000 $6,000,000 $4,000,000 Planned FY 2031 Five-Year Total $20,000,000 Appropriations to Date $7,200,000 Provide funds to…
City of Norfolk FY2027 Budget
Budget · Jul 1, 2026
Budget
47 days before RFP
The adopted CIP planned $4,500,000 for Glenrock drainage improvements to add stormwater pipes and inlets and mitigate recurring flooding.
FY 2027-2031 Adopted Capital Improvement Plan Improve Glenrock Drainage Storm Water Management Enhancing Community Beautification and Maintenance Adopted FY 2027 Planned FY 2030 Planned FY 2029 Planned FY 2028 $0 $1,500,000 $1,500,000 $1,500,000 $0 Planned FY 2031 Five-Year Total $4,500,000 Appropriations to Date $5,500,000 Provide funds to improve drainage…
City of Norfolk FY2027 Budget
Budget · Jul 1, 2026
Budget
47 days before RFP
The adopted CIP planned $950,000 for Military Highway over Broad Creek culvert channel stabilization, including $100,000 for planning and design and $850,000 for construction.
FY 2027-2031 Adopted Capital Improvement Plan Military Highway over Broad Creek Culvert Channel Stabilization Public Works Enhancing Community Beautification and Maintenance Adopted FY 2027 Planned FY 2030 Planned FY 2029 Planned FY 2028 $0 $0 $0 $100,000 $850,000 Planned FY 2031 Five-Year Total $950,000 Appropriations to Date $0 The project will repair the…
Budget
47 days before RFP
The adopted FY2027 CIP included a citywide Storm Water Utility programme for drainage improvements, system repairs and rehabilitation, system cleaning, and drainage studies.
FY 2027 - 2031 Adopted Capital Improvement Plan - Fund Summary Fund FY 2027 Adopted FY 2028 Planned FY 2029 Planned FY 2030 Planned FY 2031 Planned Five-Year Total General Fund $176,197,112 $115,550,000 $54,201,367 $59,120,489 $34,063,154 $439,132,122 Norfolk Public Schools $74,552,781 $97,000,000 $4,000,000 $4,000,000 $4,000,000 $183,552,781 Parking Fund…
RFP published
Proposals due (Closed)
City of Norfolk FY2027 Budget
Budget · Jul 1, 2026
City of Norfolk FY2027 Budget
Budget · Jul 1, 2026
These related opportunities are still open for bidding.
CityMA
Posted
Oct 6, 2026
Nov 4, 2026
Work includes approx 556 CY unclassified excvation; 1,350 LF of 12" HDPE plastic pipe; 4,840 LF of hot mix asphalt berm; 60 LF of 4' chain link fence - black.
StateAL
Posted
Oct 14, 2026
Oct 28, 2026
The State of Alabama is soliciting FY27 lawn and grounds maintenance at Pond Spring, 122880 AL Hwy 20, Hillsboro, AL 35643, for the service period October 1, 2026 through September 30, 2027. Work includes scheduled mowing with blowing and weed eating, leaf mulching and limb removal as needed, and bush-hogging and cemetery maintenance. Bidders must attend the required October 23 site visit, provide prices per line item, supply equipment and proof of insurance, and may not subcontract.
StateAL
Posted
Oct 14, 2026
Oct 28, 2026
The State of Alabama is soliciting FY27 lawn and grounds maintenance at Pond Spring, 122880 AL Hwy 20, Hillsboro, AL 35643, for the service period October 1, 2026 through September 30, 2027. Work includes scheduled mowing with blowing and weed eating, leaf mulching and limb removal as needed, and bush-hogging and cemetery maintenance. Bidders must attend the required October 23 site visit, provide prices per line item, supply equipment and proof of insurance, and may not subcontract.
OtherMD
Posted
Jul 7, 2026
Dec 31, 2026
This program will focus on small-scale maintenance projects that are $500 or less, specifically for: 1) invasive species removal/control and/or 2) plant replacements/enhancements. Funds cannot be used to purchase non-native species.
Decision makers connected to this RFP from City of Norfolk.