Summary
Work includes 1 LS trench & excavation safety; 1 LS roadway construction control; 26,537 CY unclassified excavation (plan quantity); 18,823 CY select embankment (plan quantity); 16,007 CY embankment (plan quantity); 6,750 CY undercut and backfill; 150 CY rock excavation; 1,073 CY trail undercut and backfill (sp #6); 40,619 SY subgrade preparation; 37,440 SY 4" topsoil placement (sod + seeding areas) ; 483 LF 18" reinforced concrete pipe (class iii) under pavement; 396 LF 24" reinforced concrete pipe (class iii) under pavement; 124 LF 30" reinforced concrete pipe (class iii) under pavement. See outside link.