Summary
B44 breakroom remodel. Work shall consist of the removal of the old cabinetry in room 103 and room 106 (breakroom) of B44 and the installation of new cabinets, countertops, microwaves, backsplash, a large under-the-counter refrigerator, sink, faucet, countertop water dispenser, and all necessary plumbing to accommodate these installs. The current breakroom was damaged by a water leak and must be replaced. The project shall include the following: Removal of current cabinetry, microwave, and water dispenser.
The contractor will be responsible for disposal the old units. Purchase and installation of all materials and products outlined in this summary and laid out in documentation provided. Reference the attached documentation for comprehensive list of materials needed, dimensions, etc. Provide all as-built drawings to the 184th Civil Engineer Squadron Engineering Flight (184 CES/CEN).