Summary
Work includes approx. 900 LF of cured in place pipe lining. Project consists of 5 phases. Phase 1 - pre-rehabilitation CCTV inspection shall include televising each sewer segment to document existing conditions, identify active leaks, assess pipe deterioration, locate connections, and identify potential voids. Phase 2 - structural rehabilitation shall include rehabilitation of the 36-inch by 24-inch oval sewer using a structural cured- in-place liner and rehabilitation of the 30-inch circular sewer using structural cured-in-place pipe lining. Phase 3 - lateral reinstatement shall include locating and reinstating all active storm sewer connections affected by the rehabilitation work at the completion of each workday or upon completion of each access structure-to-access structure section, whichever restores the connections sooner. See attached file.