Summary
The City of Moline is soliciting bids for the 49th Street Drainage Improvements - Phase II project, which includes construction of a new pump station, an embankment berm, chain link fencing, seeding, decommissioning of the existing pump station, and associated storm sewer and utility work. Prevailing wages apply and the city anticipates work to begin after August 17, 2026 with substantial completion by March 31, 2027 and final seeding/punch-list items by May 15, 2027. Bidding is electronic through the City’s IONWAVE e-bidding system and the bid opening will be held virtually via RingCentral; project documents are posted on the City’s e-bidding site and require login to download.