0.50 mi of hot mix asphalt reconstruction, concrete curb and gutter, storm sewer, and pavement markings in the village of Kingsley, Grand Traverse County.
Description: Contract 28000-214833 calls for 0.50 mi of hot mix asphalt reconstruction, concrete curb and gutter, storm sewer, and pavement markings in Kingsley, Grand Traverse County. The advertisement identifies it as a local-agency project, and the project listing identifies the Village of Kingsley. Bids are due at the November 6, 2026 letting at 10:30 a.m. local time, which is still in the future as of October 23, 2026.
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
521 days before RFP
The Village Council approved Wade Trim's $69,500 reconstruction proposal to finish the N. Brownson project.
See sourceHide source
3. Wade Trim Proposal of $69,500 to finish out the N. Brownson Project. Motion by Forro, seconded by Willman , to approve the reconstruction proposal. Roll Call: Yes: Lajko, Weger, Specker, Willman, Bott, Forro, No: None, Absent: McPherson. Motion CARRIED.
Wade Trim reported that the N. Brownson project had received a TAP grant and was awaiting 2026 bids.
See sourceHide source
5. Wade Trim Joe Slonecki reported on Blair St under construction on schedule to be completed by the start of school. Exploratory issues caused some unforeseen utility issues with rain has caused about a 3 day delay in the project. Large timbers found under the street caused some issues during excavation helped update records of unmapped utilities. Molan…
Wade Trim reported MDOT approval, construction planned after school lets out in 2027, and a $137,000 TAP grant with a $50,000 local match for the N. Brownson project.
See sourceHide source
5. Wade Trim Joe Slenecki updated the council that the N. Brownson project was turned in and approved by MDOT, the plan is to start construction after schools lets out 2027. TAP Grant awarded came back at funding breakdown from MDOT the grant that was applied for came back at $137,000.00, 80/20 match with everything turned in, the estimate that got turned…
Village of Kingsley Village Council Village Council Meeting
Project consists approx. 250 FT of 24" CIPP;579 FT of curb and gutter; 200 CY of masonry and concrete structure; 1,206 Ft of 12" Sewer CI A; 5,669 Ft of video inspection of underdain.
This local-agency project covers 0.51 miles of Manchester Street in Highland Park, from Woodward Avenue (M-1) northeasterly to Oakland Avenue. The work includes hot-mix asphalt cold milling and resurfacing, storm-sewer installation, concrete curb and gutter, sidewalk and ramp improvements, and signing and pavement markings. The posting identifies the City of Highland Park as the local-agency project sponsor and specifies prequalification requirements for prime contractors.