Summary
Work includes clearing and grubbing, removal of precast bridge @ 15+77.05, removal of asphalt pavements (all depths) 800.000 SY, removal of pipe (all sizes) 40.000 LF, unclassified excavation (fm) 765.000 CY, borrow excavation (contractor-furnished fme, class 9) 100.000 CY, excess excavation (fm) 143.000 CY, crushed stone 610, (lvm) 360.000 CY, 24" corrugated polyethylene pipe 40.000 LF, guardrail, w-beam, complete-in-place 50.000 LF, reflectorized traffic object marker (encapsulated lens) (type 3) 4.00 EA, agricultural limestone 0.900 Ton, commercial fertilizer (13-13-13) 1.900 Ton. See attached file.