Jea Awards Awards Meeting
The meeting addressed several agenda items, including the approval of the minutes from the January 15, 2026 meeting. Key discussion points involved a contract increase for Zammataro Jacobs Engineering Group, Inc. for design services related to the Monument Road 24-inch Reclaimed Water Main project, necessitating expanded scope for engineering and subconsultant services across multiple design and support phases. Another major item was the approval of a construction services contract via RFP for the Miller 230kV Solar Substation, awarded to Erixton Reliable Substation Services, Inc. A single-source award to GE Vernova International LLC was discussed for B50 HMI Server Replacement and Software Upgrades at Brandy Branch Generating Station due to the proprietary nature of the equipment, ensuring system reliability and NERC-CIP compliance. Public comments received via email concerning agenda items were also scheduled to be read.