Summary
Snohomish County PUD is soliciting a contractor to set a 125' steel pole (with a 22' steel casing), install required 115kV and 12kV framing, remove the existing wood pole structure, and install approximately 1,100' of new fiber optic cable between specified poles. The scope requires coordination with the City of Mountlake Terrace for tree trimming, restoration of work areas using native vegetation, and compliance with all applicable laws; contractors must be on the District’s Small Works Roster and prequalified for Category A-2 (Overhead Line Construction). The posting includes a mandatory pre-bid meeting and a budget estimate (engineer’s estimate ~$275,000; budget range $200,000–$350,000).