Summary
Street Improvements which are to include; earth excavation, removal and disposal of unsuitable materials, grading & shaping ditches, Portland cement concrete pavement 9 (jointed), culvert removal, curb & gutter, soil sampling & testing, traffic control, inlets, mobilization. Watermain Improvements which are to include; 8” watermain, fire hydrants with valve box, gate valves w/vault box, trench backfill, connect to existing watermain, pressure testing
& disinfection. Sanitary Sewer Improvements which are to include; 8” Sanitary Sewer PVC, manholes, trench backfill, sanitary sewer connections, sanitary sewer testing, and all related appurtenances.