Summary
Task 1: Main Building Roof Pre-Construction & Engineering Requirements: The contractor shall provide Wind Uplift Engineering: The system shall be engineered to ASCE 7-22 standards for high-wind coastal zones, achieving a minimum FM Global 1-90 rating. Design must withstand 75+ MPH gusts. The contractor shall submit a Safety & Staging Site-Specific Safety Plan (SSSP) and
Hoisting/Crane Plan to the designated Contracting Officer Representative (COR) for pre-approval after the Notice to Proceed, prior to start of work. The contractor shall be responsible for traffic control on Water Street and must ensure the Woods Hole Aquarium entrance remains safe and unobstructed. See attached file.