Summary
The scope of work shall include removing, storing, repairing, and reinstalling the existing clarifier mechanical equipment for Clarifier 1 and if awarded by Owner, Clarifier 2. The scope of work shall also include removal of the existing concrete slab (approx. 125 CY) and the in-situ replacement of a new concrete slab (approx. 250 CY) for Clarifier 1 and if awarded by Owner, Clarifier 2. The scope of work shall also include the removal and in-situ replacement of approx. 55 LF of 10" ductile iron pipe (DIP), 55 LF of 16 in DIP, and 55 LF of 30 in DIP under Clarifier 1 and if awarded by Owner, Clarifier 2.