Summary
Installation of approx. 560 LF of 10" DR11 HDPE gravity sewer main using the Horizontal Directional Boring and open trench methods. The project includes the installation of approx. 70 LF of 8" PVC Sewer Main, three 48" manholes, one 54" saddle manhole, and two side sewers with associated cleanouts. The project also provides for the demolition of an existing lift station, including pumping equipment, standby generator and generator enclosure, piping, valves, and other mechanical equipment. The project also includes hot mix asphalt trench patch, installation of two ADA curb ramps, driveway restoration, and general restoration. The project also provides for roadway improvements consisting of a 2" grind and hot mix asphalt overlay with pavement markings.