Summary
Work includes approx 9,124 LF of 8" sewer lines CIPP by UV light cure; 150 VF 19 manholes manhole rehabilitation by monolithic concrete liner (monoform); manhole frame and grade adjustments; pre and post CCTV and cleaning; spot repair of mains as required for CIPP lining. 1 LS mobilization / demobilization & closeout (max. 5% of total bid); 6,908 LF cleaning & pre-CCTV sewer mains (all sizes); 2 EA spot repair of existing mains, as required for CIPP lining; 4,840 SY hydro-mulching / seeding; 50 LF curb & gutter replacement; 1 LS highway 9 pump station rehabilitation; 20 EA manhole replacement (precast); 150 VF manhole rehabilitation (monoform); 5,841 LF 8" cured in place pipe (CIPP); 1,067 LF 10" cured in place pipe (CIPP); 150 SY asphalt street repair; 70 SY state highway asphalt repair. See attached file.