Summary
Construction of the running track and synthetic turf field. demo, base construction, preparation, and installation of a New Football Field with synthetic turf and an 8-lane running track with specified field event surfaces. All field markings for football and soccer for synthetic turf field and new field events for the new running track including long jump, triple jump, pole vault, and high jump areas in accordance with these specifications and conforming to standards for synthetic turf fields and running track construction. Permanent or essential equipment associated with field events will be provided as per input from the AD and coaching staff. Estimates for tangential items (hurdles, pads, equipment must be a line item as well. Demolition of site Remove all of the existing vegetation and dispose of offsite. Remove (11,000 CY) of over burden and use for areas onsite. Remove all fencing around field and dispose of offsite (re-construction of fencing may be sub-contracted as additional or alternate bid). Running Track Construction: 1. Survey the field area for new running track. 2. Remove all overburden 8” below new curb height. 3. Locate and re-fit the four existing catch basins.
4. Install new 8” X 8” curb on inside and outside of track. (See
Drawing) 5. Install 7” AB3 aggregate base on compacted subgrade at 1%
slope from outside curb down to inside curb on entire oval and
“D” area. 6. Install new high jump pad with a full “D” area. Padding and accessories as preferred by Owner. (See Drawing) 7. Pave new 4” of asphalt in two 2” lifts at 8 lane track, chute, and “D” area.
8. Construct new pole vault and triple jump runways pads and
pits per print using 6” of road base for stabilization and 5” of
concrete for surfacing; construct appropriate discus and shot
put competition areas with maximum regard to safety of participants, officials, and spectators. Padding and accessories as
preferred by Owner. (See Drawing) 9. Prime and/or otherwise prepare the asphalt or concrete base in a manner that allows for proper adhesion of the new synthetic surface specified by the manufacturer.
10. Apply a polyurethane or polyresin binder ½” (13 mm) thick
black sandwich system in accordance with manufacturer’s instructions to ensure proper bonding of resilient surface to the asphalt base.
11. Apply a structural spray coating at no less than 1000 psi to
the synthetic surface as prescribed by the manufacturer, that
incorporate specialized UV stabilizers and antioxidants to prevent fading, cracking, and brittleness. The district would like the
running track surface to be black in color with red lane markings
(See Drawing). 12. Clearly and accurately mark/paint all lines, starting lines, and event markers according to the National Federation of State High Schools Association (NSHS). 13. The contractor shall provide a written warranty for the surface
installation and paint striping against faulty materials or workmanship for a period of five (5) years from the date of acceptance from the (Owner McLoud Public Schools). Football Field:
1. Install new goal post and pin new corner markers for field.
2. Remove all of the existing overburden of football field area and
use for other areas on site. 3. All sub-grades will be graded to allow drainage system to have adequate fall to perimeter drains.
4. Install new 12” perimeter and connect to existing catch basins
(4) Contractor responsible to make sure the drains are clean
and working order. 5. Install new multiflow 6" flat drains at 20ft centers (see drawing). 6. Install 6"clean #57 stone on entire field and “D” area for proper drain base. 7. Install 1" #8 stone to bridge the drain base. 8. Grade stone base 1/4"+/- for planarity and accuracy of playing surface. 9. Install dual yarn turf of monofilament and polyethylene. 50oz in face rate and 28oz polyurethane backing. Alternating panels of Verdi green and olive green. End Zones to be in the color RED. Brockfill organic infill. (see drawing).