Summary
Work includes: 790 LF, straw wattles for erosion control; 1 LS, general excavation & grading; 1 LS, remove and dispose existing guiderail systems; 300 LF, remove and dispose drainage pipe; 64 CY, gravel subbase; 32 CY, processed gravel base; 9270 SY, pavement milling 2"; 6910 SY, full-depth cold pavement reclamation; 20 TN, temporary bituminous concrete pavement; 810 TN, HMA S0.5 binder course; 1870 TN, HMA S0.375 surface course; 300 LF, 15" HDPE drainage pipe; 2130 LF, bituminous concrete curb; 5060 SF, bituminous concrete sidewalk; 800 SY, topsoil, seed, fertilize & mulch; 11325 LF, 4" epoxy resin pavement markings yellow; 11400 LF, 4" epoxy resin pavement markings white. See attached file.