Summary
The City of Huntington, Indiana is soliciting bids for the construction of a duplex submersible lift station north of Progress Drive in the River Fork West Industrial Park, with a force main discharging to the existing gravity sewer on CR 200N. The work includes clearing right-of-way, rock excavation, a lift station wet well and valve vault, ductile iron piping and valves, a pump control panel, switchgear, site lighting, fencing, approximately 2,300 feet of 6-inch HDPE force main, horizontal directional drilling under roadways, asphalt paving of an existing stone cul-de-sac, erosion control, and surface restoration. A mandatory pre-bid meeting is scheduled for July 8, 2026 at 9:30 a.m., bids are due by July 20, 2026 at 3:30 p.m. local time at the Huntington city offices, and the Board of Public Works and Safety anticipates awarding the contract on August 3, 2026.