Summary
Storm sewer rehabilitation. Work includes Clean Out Inlet #2048 and 18" Storm Pipe to Existing 60" Storm Culvert; Cleaning of 60" Concrete Pipe Culvert. Remove and Dispose of All Silt, Debris, Vegetation, Soil, Rock, Or Any Type of Blockage to Provide Maximum Drainage Capacity. CCTV Inspection of 48" Storm Sewer Pipe. CCTV Inspection of 60" Concrete Pipe Culvert. Demolition and Removal of Existing Concrete Wall and Curbing. Provide and Install 8"x8"x8'’ Pressure Treated Lumber (As Per Detail). Provide and Install Bicycle Safe Inlet Grate, C.I. 24"x48" and Frame. Milling of Asphalt Pavement Surface, 2" Depth. Milled Material to be Retained by Contractor. Superpave Asphalt Mixture Design, HMA Wearing Course, PG 64-22, 0-0.3 Million ESAL's, 9.5mm Mix, SRL-L. Install Cast-In-Place Concrete Riser; Remove Existing Asphalt Base/Top Material. Provide and Install Concrete Road Base.