Summary
The work consists of removing and replacing the media inside the Hydrogen Sulfide reaction vessels at the Stickney Water Reclamation Plant. The Contractor is required to furnish the new Hydrogen Sulfide Removal Media, remove the spent media from both vessels, haul and lawfully dispose of the used media to a sanitary landfill, clean the vessels, inspect the vessels, install new media, and restart the system. The Contractor must provide a temporary flare system to burn the digester gas during startup of the system. The contract shall commence upon approval of the Contractor’s Bond and terminate on December 31, 2026.