Summary
This project includes phased enabling, demolition, temporary systems, installation, commissioning, and restoration required to replace air handling units, exhaust systems, chilled water infrastructure, and associated rooftop equipment. The project consists of baseline, intermediate, and final testing and balancing; installation of temporary supply and exhaust systems; selective demolition of existing AHUs, FCUs, exhaust fans, ductwork, steam and chilled water equipment; and installation and reconnection of new AHUs, rooftop exhaust fans, chilled water pumps, piping, and a new rooftop chiller integrated with existing systems. Divisions needed: 02 Demo, 03 Concrete, 05 Structural Steel, 15 Mechanical, 16 Electrical.