Summary
DESIGN-BUILD. A new secure drive for transport of detainee’s and law enforcement individuals. This will consist of the design-builder providing a concrete drive on the grassy area on the west side of building per the following illustrations. The design-builder shall remove top soil to a depth of a minimum of 10" and dispose of all material removed off-site. Provide necessary equipment to roll the subgrade for proper compaction. Furnish and install 4" of 3/4“ gravel [subbase] over the subgrade. Level gravel and roll for compaction. Furnish and install #4 rebar on two-foot centers over subbase. Furnish and pour a minimum of 6" of 4,000 PSI concrete over subbase. The new concrete drive (approx. 160 FT in length and approx. 15 FT in width) is to tie-in and merge with existing driveways at the south (fleet parking entrance) and north (warehouse delivery) and be flush with existing concrete. Float concrete for a uniform surface.