Summary
Bid Schedule A – CSPP & Electrical: Primary Work: Mobilization, Construction Safety Phasing Plan, Temporary Phasing Work, Electrical, Demolition Work, Electrical, GA Terminal Building Work, Electrical, Complete, Vault Building Work, Electrical, Complete, 6,900 Ft of 1/C No. 2 Cu AWG, 600V, THWN-2, Installed in Conduit, 3,500 Ft of 1/C No. 4 Cu AWG, 600V (GND), THWN-2, Installed in Conduit, Remove & Dispose of Existing Cable, 2,900 Ft of Trenching & Backfilling or Plowing for Conduit, 300 Ft of Plowing for Conduit, 2,900 Ft of Non-Encased, Electrical Conduit, (1) 2-Inch, Type I, Sch. 40 PVC in Trench or SDR 13 HDPE Plowed, 300 Ft of Non-Encased, Electrical Conduit, (1) 2-Inch, Type III, Sch. 80 PVC or SDR 11 HDPE Plowed 284, seven Each of Cable Markers, nine Each of L-867B (12”), Class 1A, Electrical Junction Box with Flat Etched Steel Cover and other items of related construction. Bid Schedule B – Automated Weather Observing System (AWOS III-P) Primary Work: Mobilization, AWOS III-P System, Complete and Commissioned, and other items of related construction.