Summary
This is a single contract for pulverizing, addition of base course, shaping to produce acceptable drainage and asphalt pavement construction along with several areas of removal of bad subbase material and replacement with geotextile fabric and 3-inch Breaker Run on approximately 6.25 miles of Sand Lake Road, 0.25 miles of Black Joe Road, and 1 mile of North Mole Lake Road. This contract consists of the following approximate quantities: Pulverizing and Grading (7.5 miles), EBS (3,500 cubic yards), Breaker Run (5,500 tons), Geotextile Fabric (5,000 square yards), 3/4" CABC Placement (38,500 tons), Hot-Mix Asphalt Pavement14,000 tons), and 12 to 30-inch Culvert Replacements (1,200 lineal feet).