Project is for the exterior conditions at the Beach Haven Library. The general scope of work includes, but is not limited to, the following items: a. Removal of existing paint and application of new paint to all exterior masonry and wood elements throughout the exterior of the building. b. Selective removal and replacement of various wood trims, fascia boards, rake boards, etc. c. Selective repair of existing window construction. d. Removal of existing shutters and installation of new wood shutters. e. Rehabilitation of existing steel window lintels at basement level. f. Repointing of existing brick masonry construction. g. Selective removal and replacement of existing brick masonry units. h. Installation of new HVAC Split System Unit as delineated on the Drawings. i. Construction of new elevated wood platform for the implementation of a new HVAC split-system unit.