Summary
This project includes but is not necessarily limited to demolition of pavement, excavation, cut/fill, concrete paving, construction of curb/gutter, installation of formwork, placement of asphalt, adjustment of water meter boxes, valve boxes, cleanouts, and other utility enclosures, placement of thermoplastic pavement markings, adjustment or relocation of existing landscaping, and sodding. All sidewalks shall meet accessibility requirements as much as practicable including grading and finishing to achieve required cross and running slopes, placement of detectable warning plates, and construction of ramps that do not cause ponding of or impede the flow of stormwater.