Discover opportunities months before the RFP drops
Learn more →Retrieving contract details... Hang tight!
See what competitors charge and their contract structure
Spot renewal opportunities 6-12 months before expiration
Analyze buyer's purchasing history and vendor preferences
Track expiration dates across all your target accounts
Reach decision-makers before renewal with competitive intel
Our customers win 3x more contract renewals and replacements
Premium
Clean & enrich your CRM automatically
Premium
Get complete source documentation & analysis
This contract includes 1 purchase order from Jan 1, 2026 to Jan 1, 2026
| Buyer | Vendor | Issued Date | Quantity |
|---|---|---|---|
| Delaware River Port Authority | HNTB Corporation | Jan 1, 2026 | 6967 |
Full Purchase Intelligence Available
Get complete pricing, descriptions, and financial details for all 1 purchase orders
Unlock Full Details →See what competitors charge and their contract structure
Spot renewal opportunities 6-12 months before expiration
Analyze buyer's purchasing history and vendor preferences
Track expiration dates across all your target accounts
Reach decision-makers before renewal with competitive intel
Our customers win 3x more contract renewals and replacements
This document outlines a proposal for the Delaware River Port Authority (DRPA) and PATCO to procure 9,820 tons of highway rock salt from Morton Salt, Inc. for the 2026 and 2027 winter seasons. The contract duration is two years, with a total amount not to exceed $747,935.50, split into Year 1 ($369,352.90) and Year 2 ($378,582.60). The rock salt will be distributed to various DRPA bridges and PATCO facilities for snow and ice treatment.
Effective Date
Jan 1, 2026
Expires
Effective: Jan 1, 2026
Expires:
This document outlines a proposal for the Delaware River Port Authority (DRPA) and PATCO to procure 9,820 tons of highway rock salt from Morton Salt, Inc. for the 2026 and 2027 winter seasons. The contract duration is two years, with a total amount not to exceed $747,935.50, split into Year 1 ($369,352.90) and Year 2 ($378,582.60). The rock salt will be distributed to various DRPA bridges and PATCO facilities for snow and ice treatment.
ActiveThe Delaware River Port Authority (DRPA) authorizes staff to negotiate an agreement with AECOM Technical Services, Inc. for professional engineering services. These services, for an amount not to exceed $1,281,000.00, cover the 2026 Biennial Inspection of the Ben Franklin Bridge, including hands-on inspection, report preparation, and required forms. The contract duration is 24 months.
Effective Date
Jan 1, 2026
Expires
Effective: Jan 1, 2026
Expires:
The Delaware River Port Authority (DRPA) authorizes staff to negotiate an agreement with AECOM Technical Services, Inc. for professional engineering services. These services, for an amount not to exceed $1,281,000.00, cover the 2026 Biennial Inspection of the Ben Franklin Bridge, including hands-on inspection, report preparation, and required forms. The contract duration is 24 months.
ActiveThis document is a proposal and resolution by the Delaware River Port Authority (DRPA) to engage GFT Infrastructure, Inc. for professional engineering services. The services involve the 2026 Biennial Inspection of the Commodore Barry Bridge, a requirement under DRPA's bond indentures. The Board authorized negotiations for an agreement not to exceed $1,258,600.00, following a qualification-based selection process and subsequent price negotiation. The contract is expected to commence on January 1, 2026, and last for 24 months.
Effective Date
Jan 1, 2026
Expires
Effective: Jan 1, 2026
Expires:
This document is a proposal and resolution by the Delaware River Port Authority (DRPA) to engage GFT Infrastructure, Inc. for professional engineering services. The services involve the 2026 Biennial Inspection of the Commodore Barry Bridge, a requirement under DRPA's bond indentures. The Board authorized negotiations for an agreement not to exceed $1,258,600.00, following a qualification-based selection process and subsequent price negotiation. The contract is expected to commence on January 1, 2026, and last for 24 months.
ActiveThe Delaware River Port Authority (DRPA) Board has authorized staff to negotiate and award a construction contract to Carr & Duff, Inc. for $1,341,630.00. The project involves replacing ten electrical substation cabinets on the Betsy Ross Bridge, including removal, installation of new equipment, and cleaning/painting of existing structural steel. This replacement is necessary due to the degradation of the original 50-year-old cabinets to maintain operational safety and reliability. The contract duration is 365 calendar days.
Effective Date
Dec 10, 2025
Expires
Effective: Dec 10, 2025
Expires:
The Delaware River Port Authority (DRPA) Board has authorized staff to negotiate and award a construction contract to Carr & Duff, Inc. for $1,341,630.00. The project involves replacing ten electrical substation cabinets on the Betsy Ross Bridge, including removal, installation of new equipment, and cleaning/painting of existing structural steel. This replacement is necessary due to the degradation of the original 50-year-old cabinets to maintain operational safety and reliability. The contract duration is 365 calendar days.
ActiveSee who's winning contracts, track spending trends, and identify your best opportunities before your competition.
Schedule Your Demo →Premium
Clean & enrich your CRM automatically
Premium
Get complete source documentation & analysis