South Central Connecticut Regional Water Authority
The project includes installation of a lined drying bed at the west river water treatment plant, inclusive of an underdrain system to collect leachate. A pump station is will be installed to collect drying bed leachate and precipitation and pump it up to the existing lagoons. Further, a force main connecting the pump station to the lagoon influent piping will be installed, along with lagoon desludging pumps in each lagoon.
Brownsville Public Utilities Board
Work includes water treatment residuals removal & disposal for water treatment plant no. 2 sludge drying lagoon
Brownsville Public Utilities Board
Water Treatment Residuals Removal & Disposal for WTP2 Sludge Drying Lagoon.
Santa Clara Valley Water District
Construction of the Penitencia Water Treatment Plant Residuals Management Project.
Release
Oct 01, 2025
Close
Nov 12, 2025