Buena Vista-Bethel Special Utility District
Project includes: construct one 14" casing by 8" screen deep trinity well with starter and controls.
Buena Vista-Bethel Special Utility District
Project includes: construct one - 1mg concrete ground storage tank, one pump station with three (3) horizontal centrifugal pumps, one (1) meter/starter building, with yard piping, fencing, and miscellaneous site work.
Town of Texhoma
Replacement of water well pipe and pump. The pipe should be 3" sch 80 pipe and a total of 399'. The pump needs to be a 20 HP pump with motor and shroud that will pump at a rate of 150-175 GPM. We would like to send a camera down hole to look at the well casing and at the perforations. The well currently is 433' total depth and static water level is 271'.
City of Portland
Well 37 pump and motor rehabilitation.