Cincinnati/Northern Kentucky International Airport
The work consists of upgrading the electrical service capabilities that feed the west vault placing all electrical equipment above grade. Further includes 1 ls misc electrical work; 9 qty core drilling manhole, wall, floor; 1 ls misc electrical work (hydro-excavation); 1 ls misc electrical work (flowable); 10.56 clf #400 awg cu; 2.64 clf #2/0 awg cu gnd; 161 5 lf 3-1/2" emt conduit; 15 qty 3-1/2" emt conduit fittings; 102.5 lf 3-1/2" pvc conduit; 6 qty 3-1/2" pvc conduit fittings; 10 qty hangers; 1 qty pull boxes; 1 qty pm8000; 1 qty circuit breaker in enclosure. See attached file.
West Vault Electric Service Upgrade
zip
Release
May 01, 2025
Close
May 22, 2025