Orange Water and Sewer Authority
The project includes the replacement of approx. 17,500 LF of existing 6" and 8" diameter AC water mains within the Briarcliff/Ridgefield neighborhood. These existing AC water mains will be replaced with approx.11,050 LF of 8" and approx. 4,850 LF of 6" ductile iron, along with approx. 1,600 LF of 2" PVC water main and all associated appurtenances, including water meters, fire hydrants, and connections in multiple locations to existing water mains, as well associated pavement and curb and gutter replacement, and all other associated work as described in the Specifications and as shown on the Drawings.
Briarcliff/Ridgefield Neighborhood Water Line Replacements
zip
Release
Apr 27, 2025
Close
May 29, 2025