Douglasville-Douglas County Water And Sewer Authority
Removal of approx. 36 LF of 42" corrugated metal pipe (CMP), 53 LF of 48" CMP, one concrete headwall, one drop inlet, pavement, existing trees and vegetation. Approx. 102 LF of existing 42" CMP will be abandoned, capped, and filled with grout. The Project includes the installation of approx. 164 LF of 42" reinforced concrete pipe (RCP), one cast-in-place concrete headwall, one precast drop inlet (GDOT STD. 1019A), two precast reinforced concrete manholes (GDOT STD. 1011-A), asphalt pavement, and erosion control measures. Approx. 81 LF of existing 42" CMP and 72 LF of existing 42" RCP will be centrifugally cast concrete pipe (CCCP) lined, as well as three existing structures. Protection of an existing water line, power pole, and sign and coordination with providers to relocate as required is included in the scope of the project.
202408_supportingdocs_PE-77017-NONST-2025-000000025-2024-08-21_08_37_73-35a180cb-df57-4d77-895b-b8aebe3159bf
Release
Aug 21, 2024
Close
Sep 25, 2024