City of San Diego
The project includes Complete removal of approx. 5,000 SF portion of the existing Thermoplastic Polyolefin (TPO) membrane roofing system of Building. 1. Provide and install new TPO membrane roofing system for approx. 5,000 SF of Building 1 as per Appendix F with a 20 year No Dollar Limit (NDL) roofing system guarantee and No Exclusions Warranty. Complete removal of approx. 7,500 SF portion of the exiting TPO membrane roofing system of Building 2. Provide and install new TPO membrane roofing system for approx. 7,500 SF of Building 2 as per Appendix F with a 20 year No Dollar Limit (NDL) roofing system guarantee and No Exclusions Warranty. This Scope of Work includes inspection and repair of any wood roof sheathing or framing that has deteriorated as approved by the City. Remove 6,300 SF of existing damaged plywood sheathing and framing that has deteriorated and provide 6,300 SF of new plywood sheathing and framing.
Release
Aug 13, 2024
Close
Sep 12, 2024